83. Patrol Web Integration Test — Migration Plan

Date: 2026-04-15

Status

Proposed

  • ADR-0081 — Cross-platform test architecture (read first)
  • ADR-0082 — Impact analysis & implementation example

Context

This ADR translates the migration steps from ADR-0082 into a concrete PR plan. Each PR must leave the mobile CI pipeline green. Only the final PR is a breaking change.


PR Plan

PR Type Files changed Files added Mobile CI Web CI
PR-1 Addition 0 ~40 unaffected
PR-2 Refactor ~82 0 must pass
PR-3 Addition 0 ~15 unaffected
PR-4 Addition 0 ~6 unaffected
PR-5 Breaking ~202 0 must pass first run

PRs 14 are additive and can be merged in any order. PR-5 must be a single atomic PR — splitting it will break mobile CI.


PR-1 — Abstract Robot Interfaces

Create robots/abstract/ with one interface per existing robot class. No existing file is touched.

  • New files: ~40 abstract interface files
  • Verify: flutter analyze passes
  • Outcome: Abstract contracts ready for implementations

PR-2 — Move Robots to robots/mobile/

Rename all robots/*.dartrobots/mobile/mobile_*.dart. Add implements AbstractXxxRobot to each class. Extract shared base robots for methods identical across platforms. Update import paths in scenario files.

  • Moved files: ~40 robots
  • Changed files: ~80 scenarios + base files (import path updates only)
  • Verify: flutter analyze passes + mobile CI green — confirms no logic was changed
  • Outcome: Mobile robot layer clean; shared base robots ready for web robots to extend

PR-3 — Web Robot Implementations

Create robots/web/ with web-specific implementations for feature areas where the web UI genuinely differs. Robots with identical behavior across platforms are not duplicated here — both factories will return the same mobile class.

  • New files: ~15 web robot files
  • Verify: flutter analyze passes
  • Outcome: Web interaction layer ready to be wired via factories

PR-4 — Factories & Provider Files

Create the factory layer and the conditional export provider.

factories/
├── robot_factory.dart                 # Abstract factory interface
├── robot_factory_provider.dart        # Conditional export — never changes
├── mobile_robot_factory.dart
├── mobile_robot_factory_provider.dart
├── web_robot_factory.dart
└── web_robot_factory_provider.dart
  • New files: ~6
  • Verify: flutter analyze passes
  • Outcome: Full factory graph in place; ready for TestBase to consume

PR-5 (Atomic) — Base API + All Scenarios + All Test Files

⚠️ Do not split. Merging base changes without the scenario/test file updates breaks mobile CI immediately.

base/base_test_scenario.dart — accept RobotFactory via constructor, remove RequiresLoginMixin.

base/test_base.dart — import robot_factory_provider.dart, update runPatrolTest signature.

All ~80 scenarios — update constructor:

// Before                              // After
MyScenario(super.$);                 MyScenario(super.$, super.robots);

All ~120 test files — update scenarioBuilder:

// Before                              // After
scenarioBuilder: ($) => ...          scenarioBuilder: ($, robots) => ...

Delete mixin/requires_login_mixin.dart.

The scenario and test file changes are mechanical and repetitive — suitable for bulk scripted refactoring followed by careful diff review.

  • Changed files: ~202
  • Deleted files: 1
  • Verify: flutter analyze + mobile CI green + web CI green (first successful web run)
  • Outcome: Architecture fully in place. Both platforms run from the same test files.

Flow Summary

PR-1  abstract interfaces   → flutter analyze ✅
PR-2  move robots           → mobile CI ✅
PR-3  web robots            → flutter analyze ✅
PR-4  factories             → flutter analyze ✅
PR-5  base + all call sites → mobile CI ✅  web CI ✅

Consequences

  • PRs 14 are low-risk, reviewable asynchronously, and do not affect the team's daily workflow.
  • PR-5 is large but entirely mechanical. Prioritize CI verification over line-by-line review.
  • After PR-5, the migration is complete and the new architecture is the baseline for all future test work.